-
Tue., July 24, 2012 4:02pm
Work is picking up at the mixed-oxide fuel plant under construction at the Savannah River Site near Augusta. So federal regulators are spending more time reviewing the project as it nears completion in 2016. Regulators met with the public Tuesday to answer questions and provide updates about the U.S. Department of Energy plant, which is roughly 60 percent complete.
-
Wed., April 20, 2011 3:24pm
The U.S. Department of Energy wants to redesign a nuclear reprocessing facility under construction near Augusta. The agency is struggling to find customers willing to use the experimental fuel.
-
Wed., July 15, 2009 6:02pm
Federal agency has plans to use fuel produced at controversial plant near A